These performance objectives are our project commitments for our Department of Energy customer and become part of our report card at the end of every fiscal year.
No. |
Objective |
Due Date |
71.1 |
Safety Design Strategy AMPS |
Feb. 20, 2024 (Done) |
72.1 |
DFLAW Campaign 800K gallons |
Sep. 30, 2024 |
73.1 |
Evaporator Campaign 150K gallons(ea) |
Sep. 30, 2024 |
74.1 |
Tank AX-101 Retrieval |
Aug. 15, 2024 |
74.2 |
Initiation of A-101 Retrieval |
Sep. 30, 2024 |
75.1 |
TBI Offsite Shipment |
Sep. 30, 2024* |
75.2 |
TBI Fab/Test of Extraction Equip |
Sep. 30, 2024 |
76.1 |
Liquid Effluent Reduction 2.2M gallons |
Sep. 30, 2024 |
77.1 |
Lifecycle Cost Estimate |
Mar. 31, 2024 |
77.2 |
Tank Refurb Cold Spray Equip |
Sep. 30, 2024 |
*assumes permit approval by Jan. 30 2024 |